| 
           
			Managing Risk Assignments 
           
			 
			
			Risks must be assigned to calculate their impact. If risk is not 
			assigned to any tasks or resources it will remain in risk register, 
			but probability, impact, and score will not be shown. 
			
			 
			RiskyProject has two types of risks assignment:  
			•  Global Risk Assignments – 
			Global risk assignment are those risk assignments, which have a 
			chance of affecting the project as a whole and are not limited to 
			specific tasks or resources. For example, political or weather risks 
			would be assigned as global. 
			•  Local Assignment – Local risk assignments 
			are those risks that have a chance of affecting only specific tasks 
			or resources. A local risk assignment can affect more than one task 
			or resource. For example, risks affecting the delivery of specific 
			equipment for a certain phase of a project would be assigned local. 
			You can edit or view risk assignments in the following dialog boxes 
			and views: 
			
			  
			 
			
			Each risk assignment has the following information: 
			•  Risks can be assigned to Tasks or Resources 
			•  Risks are defined by the chance of occurrence (from 0% to 
			100%). The chance can be defined per task (by default) or per 
			duration unit. For example, if there is a 30% chance that task can 
			be restarted per day. If task duration is 2 days, the chance of the 
			risk occurring per task is 60%. This chance calculation option is 
			defined for all tasks and resources for the project in the Risk tab 
			of the Options dialog box: 
			
			  
			
			  
			
			 
			• Each risk has a different outcome. Outcomes can be schedule and 
			cost related and non-schedule related, which you can customize using 
			Risk Outcome dialog (Risk menu). Standard schedule-related risk 
			outcomes are shown in the table. 
			
			  
			 
			
			  
			
			•  The Result of outcome is related to the outcomes “Fixed cost 
			increase”, “Relative cost increase”, “Fixed delay”, and “Relative 
			delay”. It defines how much the duration or cost will be increased 
			or reduced. Result of outcomes also used for non-schedule risks and 
			is defined as a percentage. For example, risk outcome “Technology 
			change” has outcome 20%. It also has a verbal definition that comes 
			from Impact labels defined in Format Risk Labels dialog (see Format 
			menu). 
			•  RiskyProject calculates Risk Impact for duration and cost as 
			a result of sensitivity analysis and displays this in the Risk 
			Register, Global Risk Assignment views and Risk Tabs for Tasks and 
			Resources. Colors are used to indicate the level of correlation 
			between the risk and project duration and cost.  
    •  Red indicates a strong correlation 
    •  Yellow a medium 
    •  Green a weak or no correlation 
			
			 
			Colors for threats are the opposite. Particular colors for the risk 
			impact value depend on the risk tolerance defined in Format Risk 
			Matrix dialog box. 
			One risk can have different outcomes or different results of 
			outcomes. For example, if a risk occurs there is a 10% chance the 
			task will restart, and 10% chance that the task will be cancelled.
			 
			
			  
			
			The Moment of risk is defined by:  
    •  Start time of Risk occurrence; 
    •  Most likely Time of risk occurrence; 
    •  Finish Time of Risk occurrence 
    • Uniform or triangular distributions 
			 
			
			  
			
			 
			Start, Most Likely, and Finish times are entered as a percentage of 
			total task duration starting from beginning of the task. 
			For example: 
    •  Distribution: Triangular 
    •  Start: 50% 
    •  Most likely: 80% 
    •  End: 100%
			 
			
			 
			This description means that by default for A new task with duration 
			10 days risk would occur after 5th day, but most likely would occur 
			on 8th day.  
			One risk can have different outcomes or different results of 
			outcomes. For example, if a risk occurs there is a 10% chance the 
			task will restart, and 10% chance that the task will be canceled. To 
			define a risk with alternative outcomes, use the same risk name for 
			the consecutive items. RiskyProject will automatically recognize 
			that this is a discrete outcome of the same risk. Each outcome will 
			be given a number (starting at 1) and all will be colored green in 
			the Mutually Exclusive Risk Alternative column (read only). 
			
			To define a risk with alternative outcomes, use the same risk name 
			for the consecutive items. RiskyProject will automatically recognize 
			that this is a discrete outcome of the same risk. Each outcome will 
			be given a number (starting at 1) and all will be colored green in 
			the Mutually Exclusive Risk Alternative column (read only). 
			
			 
			Mutually exclusive alternatives must: 
			•  have the same name 
			•  not be separated by empty rows 
			•  belong to the same category. For example, if you have the 
			same risk “Change in requirements” with outcomes Reduce Quality and 
			Fixed Delay, these outcomes will not be mutually exclusive 
			alternatives as they are different risk categories that have 
			different impacts. 
			Here is an example of risk assignments:  
			  
			
			 
			 
			 
			
			•  RiskyProject flags any mutually exclusive alternative 
			outcomes whose sum or probabilities are greater than 100% with pink 
			shading. In these cases, the calculation results may be incorrect. 
			•  Use the Indent and Outdent arrows to group risks and create 
			a risk breakdown structure. 
			 
          See
          also 
			Assigning local and global risks 
			Risks in RiskyProject
			 
           
  |