| 
           Setting up 
			risk defaults
           
          You 
			define defaults for Global and Local risks in the Risks tab. These 
			parameters are used when you create a new risk. 
			1. From the Tools menu, choose Options. 
			2. Click the Risk tab. 
			3. Enter the default settings for the chance of: 
    • risk occurrence 
    • type of outcome 
    • result of outcome.  
    The result of outcomes is used to calculate outcomes for 
			Relative Delay and Cost or Income Increase, as well as all user 
			defined risk outcomes for non-schedule risks. 
			4. Select the default distribution for the moment of risk. This 
			distribution is used to define when risk would occur during the 
			course of project. It is defined by distribution type (uniform or 
			triangular), and three parameters defining start, most likely, and 
			finish time of risk occurrence expressed as a percent of total task 
			duration starting from the beginning of the task. For example: 
    • Distribution: Triangular 
    • Start: 50% 
    •  Most likely: 80% 
   • End: 100%  
   In the above case, the default for new task with duration 10 days 
			risk would occur after 5th day, but most likely would occur on 8th 
			day.  
			5. Select the risk chance option. The chance can be defined per task 
			(by default) or per duration unit. For example, 30% chance that task 
			can be restarted per day. If task duration is 2 days, chance of risk 
			occurrence per task will be 60%. This option works for all projects. 
			You cannot have different risks with chance applied to the duration 
			unit or chance applied to the complete task for the same project at 
			the same time.
           
          See also
           
          Risks in RiskyProject 
          Setting up your project defaults 
          Setting up your projects
            |