| 
           
			Predecessors and Lags 
           
          You define information about predecessors and lags in the Predecessor 
			tab of Task Information dialog box. 
			You can use the Standard toolbar button to link tasks; however, this 
			method of creating task dependencies has limitations: 
			•  You cannot link a task (from example Task #5) to a previous 
			task (for example Task #3). 
			•  You cannot input lag, which is time delay between 
			predecessor and successor. RiskyProject allows you to setup 
			probabilistic lag with statistical distribution defined by low, 
			base, high number. 
			 
			 
			•  
			Sometimes it is convenient to use predecessor tab instead of link 
			toolbar buttons when task has multiple predecessor or if there is a 
			big difference in task Ids between current task and predecessor. For 
			example, it is not convenient to link task number 5 to task number 
			74 using toolbar buttons. 
			•  You may use Predecessor column within Gantt view to define 
			or modify predecessors. Text: “1, 2+2 days” would mean than current 
			task has two predecessors (Task 1 and Task 2 with lag 2 days). 
			 
            
          See
          also 
			Project Tasks 
          Managing Resources and Work 
          Adding constraints 
			           |