           Task
          Information Dialog: General Tab 
           
          General Tab if task information is used to define: 
          - Task
          start and finish times (low, base, and high) 
          - Task
          duration (low, base, and high) 
          - Task
          constraints 
            
          Entering
          duration is the best way to schedule the task. If you enter Start
          Time, the constraint will be set to "Must Start On".
          You you enter Finish Time the constrain will be set to "Must
          Finish On". If constraint type is "Start not early
          than" you would need to define a date, associated with the
          constraint.  
            
          You may
          also use this dialog to enter notes for the task. 
			 
            