Defining summary tasks and subtasks
Summary tasks represent groups of tasks (subtasks) that can be
logically grouped together under a larger task. In large projects
with many tasks, this is a useful method of organizing your tasks.
1. Create a task directly above the tasks that you want to group
under it. This will become the Summary Task.
2. Select the tasks that you want to be the subtasks of the summary
task you created in step 1.
3. Click the Indent button located on the Format toolbar to indent
the tasks. The indented tasks are automatically recognized as
subtasks of the summary task. If you want to move at task out from
under the summary task, select the task and click the Outdent
buttons. After you click on an Indent or Outdent button,
RiskyProject automatically recalculates the project.