			Advanced Task Management  
           
          Use the Advanced tab on the Task Information dialog box to enter, 
			review, or change supplemental task information. You can: 
			 
			Specify the task type: A characterization of a task 
			based on which aspect of the task is fixed and which aspects are 
			variable. There are three task types: Fixed Units, Fixed Work, and 
			Fixed Duration. The default task type in the Project is Fixed Units. 
			See Task Types below. 
			 
			Specify the task calendar: The base calendar that 
			you can apply to individual tasks to control their scheduling, 
			usually independent of the project calendar or any assigned 
			resources' calendars. By default, all tasks use the project 
			calendar. You can select to ignore the resource calendar. Use the 
			Working Time dialog box to modify calendars. 
			 
			Mark the task as effort-driven: In effort driven 
			scheduling the duration of a task shortens or lengthens as resources 
			are added or removed from a task, while the amount of effort 
			necessary to complete a task remains unchanged. 
			 
			Task Types 
			The three task types used in Project are: 
			• Fixed units: Fixed unit is a fixed value and any 
			changes to the amount of work or the task's duration do not affect 
			the task's units. It is a default task type. 
			• Fixed work: Fixed-work task is a task in which 
			the amount of work is a fixed value and any changes to the task's 
			duration or the number of assigned units [or resources] do not 
			affect the task's work.  
			• Fixed duration: Fixed duration task is a task in 
			which the duration is a fixed value and any changes to the work or 
			the assigned units don't affect  
			Each of the task types affects scheduling when you edit one of the 
			three elements as follows:
			 
			 
			 
			
				
					| Task Type | 
					Change Units | 
					Change 
					Duration | 
					Change Work | 
				 
				
					| Fixed 
					units tasks | 
					
					Duration is recalculated | 
					Work 
					is recalculated | 
					Duration is 
					recalculated | 
				 
				
					| Fixed 
					work task  | 
					
					Duration is recalculated | 
					Units 
					are recalculated | 
					Duration is 
					recalculated | 
				 
				
					| Fixed 
					duration task | 
					Work 
					is recalculated | 
					Work 
					is recalculated | 
					Units are 
					recalculated | 
				 
			 
			
  |