Analyzing Risk Mitigation Efforts with Multiple 
			Baselines 
			 
			RiskyProject allows you to create multiple baselines of the same 
			project. Multiple baselines can be used during the planning stage, 
			to determine the effects that mitigation your risk mitigation 
			efforts or response plans will have on the projects overall cost, 
			finish time, and success rates. You can save up to 10 baselines 
			versions of a project. 
			 
			For example, once you have created your project and run a risk 
			analysis on it, you can create a baseline. When you create the 
			baseline, you can select a level of certainty (percentile) that you 
			have decided to use for management purposes. You can then model the 
			effects of mitigation efforts or risk response plans, This modeling 
			may include adding additional activities with resources and costs as 
			well as the closing or minimizing of risks. You can then create a 
			baseline of the “mitigated” project plan and compare it with the 
			unmitigated baseline. In this way, you can decide you risk response 
			plan as defined in PMBOK: avoid, transfer, mitigate, or accept.