             Glossary 
             
             
                
            Convergence
           
                         
                     
                   
                       
                      
                       
                          
                         
                       
                   In the process of Monte Carlo 
            simulations RiskyProject monitors mean and standard deviation of project duration. 
            RiskyProject then calculates relative different between standard deviations of project duration 
            in two consecutive simulations. If convergence monitoring it turned on, the simulation will 
            stop, when this relative         
                         
                     
                   
                       
                      
                       
                          
                         
             difference is less then predefined value within a 
            predefined number of simulations. The         
                         
                     
                   
                       
                      
                       
                          
                         
             same is done for mean. Convergence parameters are 
            set in Options dialog box, Calculation tab. Convergence allows to minimize 
            number of simulation and reduce calculation         
                         
                     
                   
                       
                      
                       
                          
                         
             time, if sufficient amount of information is 
        collected.         
                                   
                         
                    
  |