			Task calendars  
          Task calendars make it possible to schedule tasks during nonworking 
			time, as defined by the project calendar or resource calendar. For 
			example, you can set up a task calendar if you have a task that 
			needs to be worked on overnight or through the weekend. 
			You create a task calendar in the Working Time dialog box as a new 
			base calendar. You then apply the base calendar to a task by using 
			the Advanced tab in the Task Information dialog box. 
			If you have applied a task calendar to a task that already has 
			assigned resources, by default, the task is scheduled for the 
			working times of resource calendars. If you want to schedule the 
			task by using only the task calendar, select the Ignore Resource 
			Calendars check box on the Advanced tab in the Task Information 
			dialog box. 
           
            See also 
          Base calendars
           
            CreateBaseCalendar
           
            Creating a new calendar
           
            Defining working time
			 
           
           |