			Setting up duration defaults 
            
          Use the Duration tab to define the calculation of task durations. 
			1. From the Tools menu, choose Options. 
			2. Click the Duration tab. 
			3. Select the time units that will be used to enter Duration and 
			Work. Duration and Work can be entered in minutes, hours, days, 
			weeks, and months. 
			4. Define default value for effort driven flag for new tasks. 
			5. Select how low and high durations will be calculated:  
    • Absolute values can be added (subtracted) to the Base 
			Duration. 
    • High and low durations are calculated by multiplying the 
			Base duration with a coefficient. You must enter the coefficients. 
    • Internally all calculations in RiskyProject are in hours. 
			The units you select are only for data entry and display.  
    • By default, Low, Base, and High durations are the same. 
			This is important as RiskyProject recommends that you use Risks to 
			calculate task durations rather than a range of uncertainty.  
    • Low and High can represent a different uncertainty range 
			depending upon the distribution that you apply. For uniform and 
			triangular distributions, Low and High represent the minimum and 
			maximum duration. For normal and lognormal distributions, the range 
			can be P1/P99, P5/P95, or P10/P90, which you define in the 
			Distribution tab of the Task Information dialog for each particular 
			task.  
           
            See also 
          Setting up your project defaults
           
           |