			Setting up calendar defaults 
            
          In the Calendar tab, you set up the default calculations for project 
			schedules. Actual project calendars are set up in the Working Time 
			dialog box. The specific calendars and type (Deterministic or 
			Probabilistic) are set up in the Main Project Settings. 
			1. From the Tools menu, choose Options. 
			2. Click the Calendar tab. 
			3. Enter in the daily, weekly, and monthly translation values in the 
			fields provided. 
			4. Select the date format in the  Output  Date  Format box. 
			5. Enter a default start date for tasks in the New Task box. New 
			tasks can be started on current date or default start date. Default 
			start date is defined in  Project >  Main  Project
           Settings >  Project  
			Start Time. If new task supposes to start on current date and 
			different date is defined in Project Start Time of the Main Project 
			Settings dialog, new task will be constrained Start not earlier than. 
			6. Use the Show Deadlines and
			Show Resources on the 
			Gantt Chart check boxes to modify what you want to view on 
			the Gantt chart.
           
            See also 
          Setting up your project defaults 
           
           |