			Resource calendars 
           
          Resource calendars make sure that work resources (people and 
			equipment) are scheduled only when they are available for work. They 
			affect a specific resource or category of resources. By default, the 
			working time settings in the resource calendar match the project 
			calendar. However, you can customize the resource calendar to show 
			individual schedule information, such as vacations, leaves of 
			absence, or equipment maintenance time. 
			When you create a resource, the default resource calendar will be 
			created. You may view this resource calendar in Working Time dialog 
			box. By choosing Working Time from the Tools menu, you can edit 
			resource calendars to indicate nonworking time. You can also create 
			or assign different base calendars for individual resources to 
			indicate specific working hours. For example, you can assign a 
			resource to a calendar that you created for carpenters who may be 
			working during a time that is different from other workers. You can 
			edit Base calendars for each resource in the Working Time dialog 
			box. 
			When RiskyProject schedules the project, it uses the resource 
			calendar to schedule the tasks that that have resources assigned. 
			For example, if a resource has a week of vacation specified on his 
			or her resource calendar, RiskyProject will not schedule the task 
			for that week. 
           
			 
			If you have resources that work alternative schedules, such as 
			part-time or the night shift, we recommend that you set up and apply 
			a separate base calendar for each shift. Use resource calendars to 
			accommodate exceptions to individual resource's working times.
           
			 
			 