| 
           
			Cost, Income, and Revenue Calculations in 
			RiskyProject 
          
          You can define cost and income associated for tasks with risks and 
			uncertainties. You can use income to perform an analysis of the full 
			life cycle of a project. Revenue is calculated as the difference 
			between income and cost. This will affect the way that RiskyProject 
			presents data in the Cost and Cash Flow views. If the project has 
			income, all cost and cash flow data is now shown as revenue where 
			costs are a negative value. In these cases, it is possible that a 
			project will have negative revenue.  
			The example below illustrates how fixed and variable (resource) 
			costs are calculated with respect to tasks and subtasks: 
			 
			 
          
			 
			The project schedule includes the summary task “Web Site Design”, 
			the summary task “Art Works”, and subtasks “Selection of art work” 
			(2 days duration) and “Purchase of art work” (0.2 days duration). 
			“Selection of art work…” has base fixed cost $200 and is assigned to 
			the Graphic Artist with rate $50.00/hour. “Purchase of art work” has 
			a base fixed cost of $400 and is performed by Purchaser with a rate 
			of $40.00/hour. The work is supervised by project manager with rate 
			$80.00/hour, but is only 10% his time is assigned to this project. 
			It is assumed that a day has eight (8) working hours. 
			 
			
			  
			 
			The Fixed cost for the summary task is calculated as the sum cost of 
			all subtasks, which do not have subtasks under them. Resource costs 
			for summary tasks are calculated as cost of all resources assigned 
			to summary task plus resource cost of all subtasks. 
			 
			A. Calculation of base fixed cost for summary task “Web Site 
			Design”: 
			Base fixed cost for “Selection of art work…” (Task 3) = $200.00 
			Base fixed cost for “Purchase of art work” (Task 4) = $400.00 
			Total = $600.00 
			 
			B. Calculation of variable (resource) cost for summary task “Web 
			Site Design”: 
			Resource cost for project manager = 17.6 hours * $80/hr / 10 = 
			$140.80 
			Resource cost for Selection of art work (Task 3) 16 hours * $50/hr = 
			$800.00 
			Resource cost for Purchase of art work (Task 4) = 1.6 hours * 40/hr 
			= $64.00 
			Total = $1004.80 
			 
			Income is calculated similarly to cost calculation. Income cannot be 
			assigned to the resources.
			 
			 
            See also
			 
			Setting up cost defaults
			 
			Adding Fixed Costs and Income to tasks
			 
			Analyzing Cost and Revenue
			 
			 
  |