User's Guide to  

RiskyProject

Back to RiskyProject
Project Risk Management and Decision Analysis 

Site search powered by Google

Adding a predecessor to a task


1. Select the task to which you want to add a predecessor.
2. Open the Task Information dialog box.
3. Click the Predecessor tab.
4. On the first row of the grid, click in the Task Name cell. A drop-down list appears containing a list of all available tasks or type
5. Select the predecessor from the drop-down list. By default, the predecessor type is Finish- Start (FS).
6. If required, enter a lag time
7. Click OK.


• You cannot make a task be a predecessor to itself
• You cannot create a schedule that it will lead to a circular relationship between tasks
• You cannot link a summary task to one of its subtasks
• You cannot link two tasks twice.


See also

Setting up your projects

www.intaver.com products      solutions      support      partners      technology      company

Copyright © Intaver Institute Inc., 2002-2009. All Rights Reserved