|
3.
Calculate and analyze results
You
click on the Calculate button to perform a simulation. Results of
simulations for the whole project are presented within the Project
Summary view. The table shows that without
risks taken into account, the project duration will be 199 days.
However, with risk and uncertainties it will be between 199 and 304 days (mean is
232 days).
Using
the charts at the bottom of the view, you can determine
the likelihood of a project finishing before a certain date. For
example, by moving the slider you can see that there is an 82% chance that
the project finish time will be earlier than July 14.
Go
to the sensitivity view and you will see all critical risks. In this
example you can see that the risk having the greatest impact on the
project schedule is the global risk "Changes based on client's
request". The success rate of the project is 100% because you do
not have risks which would cause cancellation of the project. Go to
the critical task view and you will see tasks, which affect the project
duration the most, based on results of the sensitivity analysis.
|