Cost Before Mitigation Property

This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
NTT
Posts: 25
Joined: Sun May 27, 2007 4:51 pm
Location: Boston, MA

Cost Before Mitigation Property

Post by NTT »

We have entered a value in the Cost Before Mitigation in the Custom Properties but it does not save and is replaced by another value after we run a simulation.
risk manager
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Re: Cost Before Mitigation Property

Post by Intaver Support »

The most probable cause of this issue is that the “Auto Calculation of Expected Loss” is enabled in the Risk Information > Properties tab. The feature introduced in version 7.1 automatically calculates the expected loss if the risk occurs. The calculation does not include probability. It is useful especially if the risk is assigned to multiple activities and has impacts with statistical distributions.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply