How does the maximum task duration (see deadline tab) affect the results of Monte Carlo simulations.
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Maximum task durations affect on the simulation results
It depends on the action that you select if a deadline is met.
No Actions: displays a deadline indicator but will not affect the results of the simulation
End task: ends the task any time the deadline duration is exceeded, so the simulation results will not show any duration greater than the deadline value set.
Cancel task: cancels the task any time the deadline duration is exceeded and sets the duration of the cancelled task to 0. Success rate is calculated based on the % of iterations that do not exceed the deadline duration.

No Actions: displays a deadline indicator but will not affect the results of the simulation
End task: ends the task any time the deadline duration is exceeded, so the simulation results will not show any duration greater than the deadline value set.
Cancel task: cancels the task any time the deadline duration is exceeded and sets the duration of the cancelled task to 0. Success rate is calculated based on the % of iterations that do not exceed the deadline duration.

Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com