Is there any way to specify that risks which are mitigated 100% by the mitigation plan should not be used in the calculation?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Risk is 100% mitigated
If risks are 100% mitigated, then they are no longer active and can be closed. To close a risk, open the Risk Register, select the risk and double-click on the Risk ID (far left column).
In the Risk Information dialog box > Properties > click the Closed option.

You can also sent probability the risk equals 0. It can be reflected in Risk waterfall chart of Risk Information dialog box: risk probability after mitigation can be equal zero.
In the Risk Information dialog box > Properties > click the Closed option.

You can also sent probability the risk equals 0. It can be reflected in Risk waterfall chart of Risk Information dialog box: risk probability after mitigation can be equal zero.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com