The results always show the time of day which is not really relevant for us, can we turn it off?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Date formats
Yes, RiskyProject offers a variety of date formats that you can select for presenting the results. To modify date format for your results, go to Schedule > Project Options > Calendar. From the Output date format dropdown list, select the output format.
To save this as the default format, be sure to click the Set as Default before you exit the options.