Viewing Low and High Work
Moderator: Intaver Support
Viewing Low and High Work
How can I show low and high estimates of work on Gantt View?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Viewing Low and High Work
RiskyProject comes with a Work View that displays the 3-point estimates for work based on task start time, finish time, resource allocation and calendar.

The work estimates are included in columns that can be added to other views as well. For example, if you wanted to create an ad hoc report using the Tasks Sheet report you could add the work estimates by adding columns to the view > right-click on column header and choose Insert column ….

The work estimates are included in columns that can be added to other views as well. For example, if you wanted to create an ad hoc report using the Tasks Sheet report you could add the work estimates by adding columns to the view > right-click on column header and choose Insert column ….
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com