Duration units
Moderator: Intaver Support
Duration units
Can different task have different duration units?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Duration units
The quick answer is no as the duration unit for activities is a global project setting (set for entire project). This is common to most (if not all) scheduling software.
The duration unit (hours, days, weeks etc.) are set in the Schedule tab> Settings and Options > Project Options > Duration.

The duration unit (hours, days, weeks etc.) are set in the Schedule tab> Settings and Options > Project Options > Duration.

Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Re: Duration units
In Microsoft Project you can define duration units for different tasks individually. I think it is not a good practice. I always use the same settings for all tasks. Therefore RiskyProject's way to handle duration units is quite sufficient for us.