Hello,
How can can set low duration/cost for the group of task. I would like to multiply duration on 0.9 and 1.1 to get low and high durations.
Best regards,
Fer23
Enabling low and high duration/cost for the group of tasks
Moderator: Intaver Support
Enabling low and high duration/cost for the group of tasks
Project risk management, decision and risk analysis
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Enabling low and high duration/cost for the group of tas
You assign low and high duration for the group of tasks using popup menu in any view which has task information: schedule, results of report. Here is how to do it:
http://www.intaver.com/Help4/RP_Help.ph ... Tasks.html
http://www.intaver.com/Help4/RP_Help.ph ... Tasks.html