When are you planning to release new version of RiskyProject? What new feature will it include?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
We plan to release RiskyProject version 3 last quarter 2007 - first quarter 2008. The version will include the following features:
1. Project management with risk and uncertainties using Critical Chain (CCPM).
2. Probabilistic calendars for projects and each resources
3. Probabilistic resource allocation and resource leveling
4. Improved integration with Microsoft Project, MindJet's MindManager and other project management software.
5. Improved user interface: different sets of input tables for each view.
6. Improved probabilistic and conditional branching
1. Project management with risk and uncertainties using Critical Chain (CCPM).
2. Probabilistic calendars for projects and each resources
3. Probabilistic resource allocation and resource leveling
4. Improved integration with Microsoft Project, MindJet's MindManager and other project management software.
5. Improved user interface: different sets of input tables for each view.
6. Improved probabilistic and conditional branching
Last edited by Intaver Support on Tue Jan 15, 2008 5:57 pm, edited 1 time in total.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
RiskyProject will have an additional Critical Chain View in Tracking tab. Critical Chain View will present two charts:
1. Size of project buffer versus time. It is a standard chart used in Critical Chain method. Please note that the buffer size is probabilistic.
2. Chance of project meeting the deadline. This chart is specific for RiskyProject implementation of Critical Chain.
1. Size of project buffer versus time. It is a standard chart used in Critical Chain method. Please note that the buffer size is probabilistic.
2. Chance of project meeting the deadline. This chart is specific for RiskyProject implementation of Critical Chain.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
RiskyProject 3 will be used as a client for RiskyPortfolio. If you already have a RiskyProject and wish to use RiskyPortfolio, you may purchase a portfolio component and upgrade RiskyProject to version 3.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
We did not determine a price for RiskyPortfolio yet. Please note that RiskyPortfolio is an enterprise level tool. It can be used to select, analyze and manage multiple projects at the same time.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com