How to use "Apply global risks to the task (see Global Risk View)" checkbox within Task Information?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
By default all global risks from Global Risk view will be applied to all tasks. If you don't want to apply global risks to the particular task, you can uncheck this box. If the box is unchecked only local risks will be applied to the task.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Global risk check box
The Global Risk view is no longer supported in current versions of RiskyProject. It has been replaced by the Risk Assignment View which presents all risk assignments (local and global) in a combined view.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com