Resource rate risks
Can I assign a risk to rate for resources. For example, rate can increase on 10% due to low availability of resources?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Resource rate risks
Yes, you can use the risk outcome type: rate increase to assign a risk the a resources rate. To assign a resource rate risk, open the Resource information dialog box and click Risks. Select or enter the risk name and enter a risk chance (probability) and from the Outcome Type drop-down list, select Rate increase. Finally add the relative impact, in this case 10%.

As you can see, it is possible to model the risk as a statistical distribution with 3 pt estimates. It is also possible to model rate uncertainties as an issue. To do this, enter 100% Chance and then a statistical distribution that model the rate uncertainty. In this case, we have shifted to most likely rate by 5 % and possible limits of a decrease of -10% or an increase of 12%.


As you can see, it is possible to model the risk as a statistical distribution with 3 pt estimates. It is also possible to model rate uncertainties as an issue. To do this, enter 100% Chance and then a statistical distribution that model the rate uncertainty. In this case, we have shifted to most likely rate by 5 % and possible limits of a decrease of -10% or an increase of 12%.

Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com