Assign risk to summary tasks
How can assign risk "Increase duration" or "increase cost" to the summary task?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Assign risk to summary tasks
You cannot assign risk for the summary task directly. It is because ambiguity in distributing risk outcome between different subtasks. For example you have summary task A which has two sequential subtasks B and C. If you increase duration of task A due to certain risk, it is unclear how duration of tasks B and C will increase. We recommend to assign risk to subtask. You can assign risk to all subtasks using 'Drag'n'drop' risk view. This way you can select a summary task, but actually risk will be assigned to the subtasks.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Re: Assign risk to summary tasks
We use RiskyProject version 5? Can we use risk drag'n'drop view to assign risks to summary tasks?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Assign risk to summary tasks
RiskyProject drag'n'drop view is only available in RiskyProject version 6. You need to upgrade version 5 to version 6.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com