Configuring Monte Carlo Simulations in RiskyProject
Posted: Thu Dec 04, 2025 12:35 pm
by Ken
Hey forum, I'm configuring the risk management system in RiskyProject Professional and need help with setting up Monte Carlo simulations. How do I enable distributions and set parameters
Re: Configuring Monte Carlo Simulations in RiskyProject
Posted: Thu Dec 04, 2025 12:40 pm
by Intaver Support
Monte Carlo simulations are at the heart of quantitative risk analysis in RiskyProject Professional. Proper configuration ensures accurate probabilistic forecasts for schedules and costs. Here's a detailed guide:
1. First, ensure your project schedule is loaded (import from MS Project if needed via the add-in).
2. To enable simulations, go to Schedule tab > Settings > Options > Risk tab and check Enable statistical distribution for risk outcomes.
3. Simulation settings: In Schedule tab > Options > Calculation tab, set max iterations (600+ recommended for low-probability risks, up to 30,000), enable convergence monitoring (stop when mean/SD stabilizes within a threshold), and choose a seed (auto-generated is fine).
4. Optional: Enable critical path calculation (slower but useful) and uncertainty bands for tasks (right-click tasks > Assign Uncertainty).
5. Run the simulation by clicking Calculateāmonitor the progress bar.