Configuring Monte Carlo Simulations in RiskyProject

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Intaver Support
Posts: 1065
Joined: Wed Nov 09, 2005 9:55 am

Re: Configuring Monte Carlo Simulations in RiskyProject

Post by Intaver Support »

Monte Carlo simulations are at the heart of quantitative risk analysis in RiskyProject Professional. Proper configuration ensures accurate probabilistic forecasts for schedules and costs. Here's a detailed guide:
1. First, ensure your project schedule is loaded (import from MS Project if needed via the add-in).
2. To enable simulations, go to Schedule tab > Settings > Options > Risk tab and check Enable statistical distribution for risk outcomes.
3. Simulation settings: In Schedule tab > Options > Calculation tab, set max iterations (600+ recommended for low-probability risks, up to 30,000), enable convergence monitoring (stop when mean/SD stabilizes within a threshold), and choose a seed (auto-generated is fine).
4. Optional: Enable critical path calculation (slower but useful) and uncertainty bands for tasks (right-click tasks > Assign Uncertainty).
5. Run the simulation by clicking Calculate—monitor the progress bar.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply