by Intaver Support » Sun Jul 15, 2007 3:31 pm
RiskyProject does not present statistical distribution associated with resource allocation. However you may view low, base, and high estimates for resources using resource view. Use checkboxes on the right pane of the view to select low, base, or high resource allocation charts.
You can select four different types of resource charts:
· Peak units: The highest level at which a resource is scheduled for all assigned tasks during a given period.
· Work: Total number of hours a resource is scheduled for all assigned tasks during a given period.
· Overallocation: A resource is overallocated when it has more work assigned than can be done in the resource's available time. Overallocation is number of hours a resource is scheduled for all assigned tasks over resource's available time. Overallocation can be presented only for work (not material) resources.
· Percent allocation: The percentage of a resource's capacity taken up by all its assigned tasks during a given period. Percent allocation can be presented only for work (not material) resources.
Intaver Support Team