Yes, you may define risk 'Increase duration' or 'restart task' as well as risk 'Increase cost'. We don't have specific risk 'increase cost and duration'. But you may create two separate risks and use risk correlation mechanism to ensure that they occur together. Please remember, this 'increase cost' risk is related to fixed cost only.