Risk Chart

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
MichaelTR
Posts: 1
Joined: Fri Jun 19, 2009 8:39 am

Risk Chart

Post by MichaelTR »

When I open the risk chart view all the task bubbles are centered in the middle of the chart.

Is there a reason for this or is this a bug?
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Risk chart issue

Post by Intaver Support »

Obviously the risk chart is a bubble chart, and the most likely reason why they are all centered in the middle is that you are viewing Total Task Cost (vs Total Task Duration). If there are costs associated with the activities the you will see the activites all located on the (0,0) axis. Switch to Task Duration as the metric and the risk chart should display correctly.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Jason
Posts: 39
Joined: Wed Nov 09, 2005 10:46 pm

Re: Risk Chart

Post by Jason »

When I print risk (bubble) chart diameter of bubbles does it seem to be too small. The location of circles is correct. Relative diameter of each circle representing cost or duration is also correct. I recommend increasing diameter of circles for printing.
Jason
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk Chart

Post by Intaver Support »

Thank you for your suggestion. We will adjust the diameter of the circle in the upcoming release for printing. Please note that may also copy chart to clipboard to paste it to other software, such as PowerPoint.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Fer23
Posts: 19
Joined: Tue Apr 10, 2007 8:22 am
Location: USA
Contact:

Re: Risk Chart

Post by Fer23 »

In Risk chart I never saw red or yellow circles. When red or yellow circles suppose to appear?
Project risk management, decision and risk analysis
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk Chart

Post by Intaver Support »

Most likely you have project schedule with balanced risks: siginificant risks are assigned to task with longer duration or higher cost.

Here is some information about risk chart and how risk chart supposes to look like:
http://www.intaver.com/Help4/RP_Help.ph ... Chart.html
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Rtgorwer
Posts: 21
Joined: Wed Jan 10, 2007 4:10 pm
Location: France

Re: Risk Chart

Post by Rtgorwer »

Is possible to print Risk Chart?
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Re: Risk Chart

Post by Intaver Support »

Yes. You can print Risk Chart.

Simply open Risk Chart (Analysis Tab). Click on File -> Print or File -> Print Preview.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com