I'm trying to import schedule from Primavera to RiskyProject. The project has around 10000 activities. Can I do so?
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Post by Intaver Support »

RiskyProject has la imitation: you cannot create more than 5000 activities. However in RiskyProject 3.0 we are planning to remove this limitation.