I would like to see a statistical distribution for the duration of one of the phases of the project. What should I do?
Regards,
D.k.
Project Manager
Distribution for the project phase
Moderator: Intaver Support
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
To view results of analysis on the particular phase to can double click on gantt bar associated to the phase's summary task, phase's milestone, or the last task of the phase.
You will be presented with four requency charts:
1. Cost of the task (phase)
2. Duration
3. Start Time
4. Finish Time