I downloaded RP few days ago. I like simplicity and emphasize on event rather than on statistical distributions.

Could you tell me how do you calculate success rate?

Regards,
Sandra,
Nissan Canada

Posted: Tue Aug 15, 2006 7:37 pm
by Intaver Support
Success rate is reduced when task is canceled. A task can be canceled in one of three cases:


1. If the outcome Cancel task or Cancel task + all successors occurs, this cancels the tasks plus all successors which have occurred;
2. If a task reaches a deadline, and action associated with deadline is set to cancel task; and
3 If a project has reached a deadline and task finish time is beyond the deadline.