Importing schedule from Microsoft Project
Moderator: Intaver Support
-
- Posts: 15
- Joined: Mon Jul 09, 2007 6:54 am
Importing schedule from Microsoft Project
How many tasks can I import from Microsoft Project?
Construction Engineer, PMP
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Importing schedule from Microsoft Project
You can import any number of tasks from Microsoft Project. The limitation is only your computer's memory. Please note that if you have integrated project schedule (with many projects and sub project) and your are working with master schedule, total integrated schedule will imported to RiskyProject. For example, if master schedule has 60 tasks, integrated schedule could have 20,000 tasks. Analysis of such schedules can make some time. Also please note that if you define project schedule in RiskyProject, maximum number of tasks is 20,000.


Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com