Page 1 of 1
How are deadlines used in Monte Carlo Schedule Risk Analysis
Posted: Thu Oct 08, 2015 12:19 pm
by Ken
We normally have deadlines defined in our schedules from Microsoft Project. How are they used in RiskyProject and will they affect the results of our schedule risk analysis.
Re: How are deadlines used in Monte Carlo Schedule Risk Anal
Posted: Thu Oct 08, 2015 12:21 pm
by Intaver Support
RiskyProject will recognize deadlines if they are defined in MSP or they can be set in RiskyProject after you have imported your schedule. Deadlines have 3 different options and are set in the Task Information > Deadlines for each task.
No Actions: the deadline can be used only as a visualization on the Gantt chart
End Task: the task will end at the deadline set and this will impact the results of the monte carlo schedule risk analysis.
Cancel Task: the task will be cancelled and this number of times the task is cancelled will be reflected in the Success Rate chart.
