Moment of risk

Posted: Sat Apr 01, 2006 9:57 pm
by WayneDavidson
Sorry, just one more, I was reading through your documentation and cam across moment of risk. What does it mean and how do I use it?

Moment of risk

Posted: Sat Apr 01, 2006 10:01 pm
by Intaver Support
Moment of risk is defined by
The moment of risk is uses in tracking to automatically calculate the chance of a risk for partially completed tasks, in task cancellation, in risk "restart task". So iif you put a trianglar distribution for a risk that start at A% of the task duration, and has a most likely at B and ends a C, RiskyProject uses this disrtibution to calculate the remaining chance that the risk can occur.

Again, thanks

Posted: Sat Apr 01, 2006 10:02 pm
by WayneDavidson
Thanks for the example on moment of risk. It is a hard one to get your head around.

WD