I use RiskyProject to schedule my construction project. I have a number of risks related to material resources. It is mostly related to quality and delivery time.
How to do it?
Resource risks
Moderator: Intaver Support
Resource risks
Business Development Manager
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
You can assign risks to resources the same way as you assign risk to tasks. Here is the difference. The risk may occur in all tasks this risk is assigned to. If resource is used on 50% for the particular task, probability of the risk will reduce on 50%.