Risk Reponse Planning
Moderator: Intaver Support
Risk Reponse Planning
Does R.P. have PMBOK type risk response planning i.e. response classification (accept, mitigate, etc.) and indentification of mitigation activities?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
We don't define particular category of risk response, however you can use our risk mitigation view to define mitigation plan. Actually they are events, which are executed when risk called "execute mitigation plan" has occurred.
Intaver Support Team
Intaver Institute Inc.