Enter Completion Date for a Risk
Moderator: Intaver Support
Enter Completion Date for a Risk
How do I to enter the Due Date/ Expected completion for the risk?
Jason
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Enter Completion Date for a Risk
It can be done using RiskyProject dialog box. To invoke Risk Information go to Risk Form tab. In the Timeline box, edit End Date field.
It is also possible to at a Date type property to the Properties and then add that to the Risk Form by clicking the Edit Risk Form Layout button and adding this Completion Date property to the Form. However, you still would need to either close the risk if it ends without occurring or it becomes an issue which would make it 100% probability.
It is also possible to at a Date type property to the Properties and then add that to the Risk Form by clicking the Edit Risk Form Layout button and adding this Completion Date property to the Form. However, you still would need to either close the risk if it ends without occurring or it becomes an issue which would make it 100% probability.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com