Enter Completion Date for a Risk

General discussion and questions about project risk management and risk analysis software RiskyProject. Includes discussion on how to perform efficient project risk analysis using our software.

Moderator: Intaver Support

Post Reply
Jason
Posts: 39
Joined: Wed Nov 09, 2005 10:46 pm

Enter Completion Date for a Risk

Post by Jason »

How do I to enter the Due Date/ Expected completion for the risk?
Jason
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Re: Enter Completion Date for a Risk

Post by Intaver Support »

It can be done using RiskyProject dialog box. To invoke Risk Information go to Risk Form tab. In the Timeline box, edit End Date field.

It is also possible to at a Date type property to the Properties and then add that to the Risk Form by clicking the Edit Risk Form Layout button and adding this Completion Date property to the Form. However, you still would need to either close the risk if it ends without occurring or it becomes an issue which would make it 100% probability.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply