Can Deadline be used to automatically adjust schedules
Moderator: Intaver Support
Can Deadline be used to automatically adjust schedules
I am trying to set a dead as the absolute latest a project can finish, therefore any risks or delays in tasks should result in them being set to start earlier with the results Gantt. Do you know if this is possible? I am trying to have the risk show tasks having to start earlier to meet the fixed deadline rather than extend out beyond it.
risk manager
-
- Posts: 1005
- Joined: Wed Nov 09, 2005 9:55 am
Re: Can Deadline be used to automatically adjust schedules
With deadlines the results will only show that it fails to meet the deadline. It does not compress the schedule as you would like. Typically, schedule compression or acceleration requires a complete rework of the schedule including adding additional resources, more parallel activities. etc as required.
The only thing we can offer is generating a new schedule from the results using the export to xml feature. In this case you would have to find p level that meets the deadline. However, this schedule could be very optimistic depending upon the P level selected.
The only thing we can offer is generating a new schedule from the results using the export to xml feature. In this case you would have to find p level that meets the deadline. However, this schedule could be very optimistic depending upon the P level selected.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com