Criticality Index

Post by RiskGuru » Wed Aug 03, 2022 3:20 pm

How do I see the % of time (across iterations) that a particular task is on the critical path (“% criticiality”)?

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Criticality Index

Post by Intaver Support » Wed Aug 03, 2022 3:23 pm

1. Turn on the critical path calculation. This will impact performance as CP requires both a forward and backward pass through the schedule. Here is how to do this RiskyProject Help Content (intaver.com)
2. Add the criticality index column to the Result Gantt view.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com