Split Tasks
Moderator: Intaver Support
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Split Tasks
RiskyProject will read in a split tasks, Start and Finish Time will be read in from MSP, but the duration will be calculated using the start and finish times of the tasks using the project calendar. In the example below, you can see the Gantt bar in RiskyProject is shown as split in Microsoft Project.


Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com