Split Tasks

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
Ken
Posts: 67
Joined: Wed Nov 09, 2005 9:47 am
Location: California

Split Tasks

Post by Ken »

Do you support split tasks from MS Project?
Ken the PM
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Re: Split Tasks

Post by Intaver Support »

RiskyProject will read in a split tasks, Start and Finish Time will be read in from MSP, but the duration will be calculated using the start and finish times of the tasks using the project calendar. In the example below, you can see the Gantt bar in RiskyProject is shown as split in Microsoft Project.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply