Percent completed for summary tasks
Moderator: Intaver Support
Percent completed for summary tasks
How risky project calculates percent completed for the summary tasks and complete project if different subtasks have different percent completed?
-
- Posts: 1024
- Joined: Wed Nov 09, 2005 9:55 am
Re: Percent completed for summary tasks
Sometimes different subtasks have different percent completed. In example below percent completed for subtasks are 0%, 50%, and 100%. Percent completed for summary tasks are calculated automatically. In this example it equals 72%.

Percent completed for subtasks are defined in Tracking tab of Task information dialog box. Percent completed for summary tasks are read only. It is calculated based on algorithm implemented in Microsoft Project and other project management software. It takes into an account percent completed for all subtasks.

Percent completed for subtasks are defined in Tracking tab of Task information dialog box. Percent completed for summary tasks are read only. It is calculated based on algorithm implemented in Microsoft Project and other project management software. It takes into an account percent completed for all subtasks.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com