Project duration is shorter than expected

This forum containts questions about RiskyProject project risk analysis and risk management software: features, issues, problem reports. If you have any problems or question, please submit it here.

Moderator: Intaver Support

Post Reply
NTT
Posts: 25
Joined: Sun May 27, 2007 4:51 pm
Location: Boston, MA

Project duration is shorter than expected

Post by NTT »

We have assigned risks to the project schedule and the Low result we get seems unreasonably short. Do you know of any reasons for this?
risk manager
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

Re: Project duration is shorter than expected

Post by Intaver Support »

Often when we do unexpected results, we do recommend a reality check. It could be the results of an error in the schedule logic or in the risk assignments. If the schedule logic is sound, then most likely if you are model impacts using statistical distributions, the low or optimistic values for the ranges are too optimistic and the combination of risks impacts is giving you the result you are seeing.

In addition, if you are using the risk outcome End Task, Cancel Task, or Cancel Task and all successors this can have an unexpectedly dramatic impact on the project duration, such that it ends early, but not successfully.

Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com
Post Reply