Links to external activites

Post by Hato »

Normally our projects are going to have links to an external master project. Currently, when performing risk analysis, we remove this links manually and insert a nomincal task that has similar start and finish dates.
When I import our projects into RiskyProject the links do not even appear. Is there a workaround this?
Project manager
Intaver Support
Posts: 1024
Joined: Wed Nov 09, 2005 9:55 am

External links

Post by Intaver Support »

In RiskyProject 3.2 there external links are ignored, this is due to the limitations of the MS project xml or the mpx formats that we use to read in project schedules.

We are currently developing a solution for this that will be incorporated into version 4. This will read the external link data, but will not read in the lnk data as a whole, rather the external dates will be handled using constraints.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com