Page 1 of 1

Schedule Reports that show Uncertainty Bands.

Posted: Sun Jun 06, 2021 12:40 pm
by Jason
Is there a report within Risky Project that shows the individual uncertainties that have been added for some tasks in the schedule? For example we used Duration Bands to set some individual uncertainties on certain tasks. We would like some way to have a "report" of this besides scrolling through the whole schedule in Risky Project to find the color coded lines.

Re: Schedule Reports that show Uncertainty Bands.

Posted: Sun Jun 06, 2021 12:45 pm
by Intaver Support
Short answer is no. I was thinking that they could be flagged in a text column and filtered but our Text columns do not support filtering.
Workaround might be to use a Text Column to flag activities that use Risk Bands > Export the Schedule the Excel and apply the filter to the target column (Risk Bands).

Image

Re: Schedule Reports that show Uncertainty Bands.

Posted: Thu Jul 27, 2023 12:58 pm
by Intaver Support
It is important to note that all information about Uncertainty Bands in RiskyProject Enterprise are saved into the Enterprise database. As a result the users in one organization will be able to share settings for the uncertainty bands. Only administrator are able the edit and save these settings. This process helps to make uncertainty band settings consistent across the organization.