Saving Results to Baselines

This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
KerryMiller
Posts: 23
Joined: Tue Dec 18, 2007 3:39 pm
Location: USA, MI

Saving Results to Baselines

Post by KerryMiller » Sat Feb 22, 2020 5:46 pm

There is not an option to select probabilistic data baseline. Even after disabling risks and uncertainties. Only options given are deterministic, low, base, high and results based on percentile.
Project Engineer

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Saving Results to Baselines

Post by Intaver Support » Sat Feb 22, 2020 5:51 pm

With all previous versions prior to the release of version 7.1, probabilistic results were not saved with baselines. All risk and uncertainties could be saved, but you can only view the deterministic results in the Manage Baseline views. Previous version is shown below.
Image

In version 7.1, the Set Baseline dialog box now includes the option to save the results with a baseline.
Image

However, even though the results of the simulation are saved with the baseline, in the Manage Baselines dialog box, the data that is shown is still the deterministic values, not the “risked” values.
Image

You must still select the baseline “x” and click OK to view the simulation results.
If multiple baselines exist, you can view the difference between the status of a risk in the different baselines in the Risk Information > Risks in Different Baselines tab.
Image
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com