Integration with Asta PowerProject

This forum focus on project portfolio risk management theory and RiskyProject Enterprise software. Submit any questions about enterprise risk management, and qualitative / quantitative risk analysis for multiple projects. This forum also includes discussions about project risk analysis on the enterprise level.

Moderator: Intaver Support

Post Reply
David
Posts: 19
Joined: Tue Jan 15, 2008 4:33 am
Location: UK

Integration with Asta PowerProject

Post by David » Mon Jun 10, 2019 4:36 pm

Can you read schedules from Asta PowerProject?
PMP, M.Sc.

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Integration with Asta PowerProject

Post by Intaver Support » Mon Jun 10, 2019 4:38 pm

Yes. Both Asta PowerProject and RiskyProject support MSP xml. Therefore you can save your PowerProject file in one of these formats and import into RiskyProject using the File>Import> <file type> command.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Intaver Support
Posts: 992
Joined: Wed Nov 09, 2005 9:55 am

Re: Integration with Asta PowerProject

Post by Intaver Support » Sun Oct 04, 2020 9:50 pm

We have many clients who asked as did we actually tried to performed risk analysis based on schedules created in Asta Powerproject. Yes. We tried many schedules created in Asta and import them to RiskyProject. Asta and RiskyProject are compatible with each other. You can use both XML export from Asta and XER (Oracle Primavera format) export. The process of export schedule from Asta and import it in RiskyProject is fast and easy.
Intaver Support Team
Intaver Institute Inc.
Home of Project Risk Management and Project Risk Analysis software RiskyProject
www.intaver.com

Post Reply